This shows you the differences between two versions of the page.
| Both sides previous revision Previous revision Next revision | Previous revision | ||
|
bw2:workflow_schedules_new [2024/01/05 17:10] wgates [Creating a Schedule] |
bw2:workflow_schedules_new [2024/01/08 12:08] (current) wgates [Notes Tab] |
||
|---|---|---|---|
| Line 17: | Line 17: | ||
| * The Schedule information window opens. This is where the schedule for this workflow is maintained. | * The Schedule information window opens. This is where the schedule for this workflow is maintained. | ||
| - | {{ :bw2:bizweaverschedules2.png |}} | + | {{ :bw2:scheduler.png |}} |
| * 3. **Status** Indicates if the schedule is on or off. | * 3. **Status** Indicates if the schedule is on or off. | ||
| * **Schedule will not run if off is selected** | * **Schedule will not run if off is selected** | ||
| Line 45: | Line 45: | ||
| {{ : | {{ : | ||
| * 3. The options in this section change depending on the type of schedule selected. | * 3. The options in this section change depending on the type of schedule selected. | ||
| - | * **Daily** \\ {{ :bw2:bizweaverschedules5.png |}} | + | * **Daily** \\ {{ :bw2:daily.png|}} |
| ---- | ---- | ||
| - | * **Weekly** \\ {{ :bw2:bizweaverschedules6.png |}} | + | * **Weekly** \\ {{ :bw2:weekly.png? |}} |
| ---- | ---- | ||
| - | * **Monthly** \\ {{ :bw2:bizweaverschedules7.png |}} | + | * **Monthly** \\ {{ :bw2:monthly.png? |}} |
| * Day Option - Can select a day within a month to run for a select interval of months. | * Day Option - Can select a day within a month to run for a select interval of months. | ||
| * **Example** the 1st day of Every 1 Month will run once a month on the first day of that month. | * **Example** the 1st day of Every 1 Month will run once a month on the first day of that month. | ||
| Line 60: | Line 60: | ||
| ====== Run Times Tab ====== | ====== Run Times Tab ====== | ||
| * 1. **Run At** defines a specific time a schedule should run during a day. | * 1. **Run At** defines a specific time a schedule should run during a day. | ||
| - | {{ :bw2:bizweaverschedules8.png |}} | + | {{ :bw2:runat.png? |}} |
| * 2. **Run Continuously** defines a schedule running all day during the selected schedule type. | * 2. **Run Continuously** defines a schedule running all day during the selected schedule type. | ||
| - | {{ :bw2:bizweaverschedules9.png |}} | + | {{ :bw2:continuously.png? |}} |
| * 3. **Run Every** defines a schedule running during a set interval of time | * 3. **Run Every** defines a schedule running during a set interval of time | ||
| Line 75: | Line 75: | ||
| * Note the interval period cannot be longer than the From-To period | * Note the interval period cannot be longer than the From-To period | ||
| * **Do Not Run Between** - defines a period that the workflow will not run within any given schedule. | * **Do Not Run Between** - defines a period that the workflow will not run within any given schedule. | ||
| - | {{ :bw2:bizweaverschedules10.png |}} | + | {{ :bw2:runevery.png?|}} |
| ====== Exclusions Tab ====== | ====== Exclusions Tab ====== | ||
| Line 83: | Line 83: | ||
| * Clicking the add button adds another exclusion. | * Clicking the add button adds another exclusion. | ||
| * When the exclusion date has passed the " | * When the exclusion date has passed the " | ||
| - | {{ :bw2:bizweaverschedules11.png |}} | + | {{ :bw2:exclusion.png? |}} |
| ====== Notes Tab ====== | ====== Notes Tab ====== | ||
| This tab allows notes to be entered for a schedule. | This tab allows notes to be entered for a schedule. | ||
| - | {{ :bw2:bizweaverschedules12.png |}} | + | {{ :bw2:notes.png |}} |
| - | ====== Notifications Tab ====== | + | ====== Notifications Tab (2.7.8) |
| <WRAP center round tip 60%> | <WRAP center round tip 60%> | ||